Cost loaded Schedule

Mudasir DijooMember for 15 years 8 months
Created
4
1
0

Hi everyone,

i am new to primavera 6, i want to load BOQ cost to the baseline schedule, i am loading cost as a resource for that i have created one resource COST, which is a non labor type, price/uint is 1, default units/time is 1/d  and max units/time is 1/d for this resource, So when i trying to load cost of any activity as Budgeted Cost the Budgeted Units are getting divided by 8. 

Budgeted Cost and Budgeted Units for an activity should be same.

Is this because we have 8 hours work/day in the Calendar assigned to the project  

Please help in this matter

Regards

Mudasir

4 replies

Oldest first
  1. 0
    Yaser A. Al-Bustanji ·

    Dear MudasirYou must convert

    Dear Mudasir

    You must convert the unit of time to "day"

    to do that go to "edit" then choose "user prefernces" the choose "time units" the under "units formats" and "duration formats" choose "day"

     

    Regards

  2. 0
    Raymund de Laza ·

    Hi, Use the Material Resource

    Hi,

    Use the Material Resource Type instead.

     

     

    Regards,

  3. 0
    Mudasir Dijoo ·

    Thanks Yaser and

    Thanks Yaser and Raymund,

    units formats n duration formats is already Day, Changed labor resource type to material resource type, now it is working

    Budgeted unit is equal to Budgeted cost.

    Regards

    Mudasir

  4. 0
    Mudasir Dijoo ·

    Thanks Yaser and

    Thanks Yaser and Raymund,

    units formats n duration formats is already Day, Changed labor resource type to material resource type, now it is working

    Budgeted unit is equal to Budgeted cost.

    Regards

    Mudasir