Cost loaded Schedule
- Created
- 4
- 1
Hi everyone,
i am new to primavera 6, i want to load BOQ cost to the baseline schedule, i am loading cost as a resource for that i have created one resource COST, which is a non labor type, price/uint is 1, default units/time is 1/d and max units/time is 1/d for this resource, So when i trying to load cost of any activity as Budgeted Cost the Budgeted Units are getting divided by 8.
Budgeted Cost and Budgeted Units for an activity should be same.
Is this because we have 8 hours work/day in the Calendar assigned to the project
Please help in this matter
Regards
Mudasir