Fragnet function/option in P6

Fernando TubiaoMember for 17 years
Created
2
3
0

What is the equivalent of P3's Fragnet option in P6? I have a set of activities that I'd like to copy and then bring them back to make just some changes, just the way we used to do it in P3. Thank you in advance. 

2 replies

Oldest first
  1. 0
    Ayman Eleish ·

    Dear Fernando, What I came to

    Dear Fernando,

    What I came to know that ther is no fragnet in PY,however you can do the same via copying the WBS as a hall.

    Regards,

  2. 0
    Frederic Fasquelle ·

    You can also basically

    You can also basically copy/paste, click on setting "only between copied activites" to avoid duplicate links,

     

    Frederic