Strange thing with schedule % complete

Ravirg GehlotMember for 15 years
Created
6
1
0

Hi
Well I am watching a strange thing with schedule % complete when i run the schedule The schedule % complete changes and within a 3-4 seconds again the Old figure of Schedule % complete apperres in the schedule ...Its Like Suppose initally Schedule % comp. is 5% and when i run the schedule after DD+15 days ...The schedule % comp just after running appear 8.2% and within a same minute Its Going back again at 5 % ....I run the schedule with DD+100days then also the same figure 5% is showing as schedule % complete...Is it not strange ?

6 replies

Oldest first
  1. 0
    Raymund de Laza ·

    Hi,What does you mean by

    Hi,

    What does you mean by running the schedule after DD+15 days? Did you mean changing the DD to a new date 15 days later?

  2. 0
    Ravirg Gehlot ·

    Yes , If i run the schedule

    Yes , If i run the schedule Dd+7 days , do i get a scheduled progress after 7 days , its like today is 1.1.12 & I want to make a Forecast plan for next week ...& i run Dd+7 days schedule it then will this be Next weeks Plan ?

  3. 0
    Jenny Ingco ·

    Ok, before you hit run..

    Ok, before you hit run.. change the options and make everything as Default then hit run schedule.

  4. 0
    Ferdinand U. ·

    did you assign a baseline?

    did you assign a baseline?

  5. 0
    Jerome Soriano ·

    Hi ravirg,Schedule % Complete

    Hi ravirg,

    Schedule % Complete = Planned Value Cost @ any Data Date/Baseline Budgeted Total Cost

    This is how primavera summarizes schedule % complete. Schedule % complete depends on the cost loaded baseline schedule.

    If the cumulative loaded cost in the baseline does not change after period of time, then the schedule % complete is also the same throughout that period.

     

     

     

     

  6. 0
    Jerome Soriano ·

    Hi ravirg,Schedule % Complete

    Hi ravirg,

    Schedule % Complete = Planned Value Cost @ any Data Date/Baseline Budgeted Total Cost

    This is how primavera summarizes schedule % complete. Schedule % complete depends on the cost loaded baseline schedule.

    If the cumulative loaded cost in the baseline does not change after period of time, then the schedule % complete is also the same throughout that period.

     

     

     

     