Reource schedule
In the Open Standard
Sudarshan SinghMember for 15 years 5 months
- Created
- 6
- 1
0
Dear All,
Can we do in Primavera the following condition, if yes please explain.\
- Say we have planned for 350 Sqm Shuttering to be completed in two weeks. Planned quantity for 1st week is 200 Sqm & that for the 2nd week is 150 Sqm.
- Requirement of daily resources for 1st week is Carpenters – 15, Helpers – 30 and that for 2nd week Carpenters – 20, Helpers – 40.
- At the end of 1st week, we have completed 130 Sqm but still want to keep the finish date same.
Sudarshan
6 replies