Issue on layout between baseline and current tasks
In the Open Standard
Frederic FasquelleMember for 20 years 7 months
- Created
- 0
- 4
0
Hi,
I am facing a small issue on my layout.
When I display current bar together with baseline bar, links appear between baseline activities and not on current ones.
Moreother, let say that I assigned a Text on left of tasks. My project has been delayed, thus my current tasks are pushed to right. But, text continue to stick on left side of baseline, while it should be on current task.
It may come from a parameter or an option that I have not yet discovered,
Thanks for any help,
Frederic
Replies
Oldest firstNo replies yet. Be the first to answer.
Log in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?