when a successor starts before its predecessor ... ...
In the Open Standard
Forrest ChenMember for 14 years 9 months
- Created
- 4
- 2
0
Hi there,
Now I am having a problem which has been killing my brain cells for the past few days.
when I was trying to update my schedule in P6, I found out that in reality, some of the work sequence has changed, successor started before its predecessor, when I update accordingly, the gantt chart looks weird (there are blank/space in a bar )and the durations become incorrect. any solution will be highly appreciated, thanks.
Forrest
4 replies