baseline

Mahmoud El ShamyMember for 14 years 8 months
Created
2
2
0

hi my friends

how can i make import or export in p6 without loosing the baselines

because every time when i made export from p6 i lose the baselines

with best regards

mahmoud el shamy

2 replies

Oldest first
  1. 0
    Ranjiv Kurup ·

    Create a copy of the current

    Create a copy of the current baseline.

    Restore the copy.

    Export the restored baseline copy with project.

     

    To import:

    Import both projects (XERs).

    Use the "Convert another project to a new baseline of the current project" feature.

  2. 0
    Mahmoud El Shamy ·

    dear ranjiv

    dear ranjiv kurup

    thaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaank you 

    i cant describe the words

    i am really really thank you

    eng mahmoud el shamy