Skip to content

Level of Effort (LOE) for Cost Summation

Planning guyMember for 15 years 3 months
Created
2
2
0

Hi

 

I am using P6, i have following problem

I have huge project with many activities, i want to add up duration of few consectivite activities , I have defined a dummy activity , assigned it a Level of effort activity type (LOE) , and assigned SS to Predessor and FF to successor ,

Now this dummy activity is summing up the duration , its fine , but its not summing up the budgeted costs . Its showing 0 cost.

Why is it soo...??????

Kindly help.

2 replies

Oldest first
  1. 0
    Raymund de Laza ·

    Hi, Advices you to use the

    Hi,

    Advices you to use the Activty Coding.

  2. 0
    Brian Fletcher ·

    You would have to add the

    You would have to add the resource/cost to the Level of effort as well. The Level of effort is in itself another activity but doesnt work in the same way as a summary bar would in MS Project?

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?