Open ended tasks on critical path
- Created
- 4
- 5
Hi all,
I have an issue with open ended tasks ina plan. I'm analysing the plan with Primavera risk analyser and the open ended tasks in the plan are lying on the critical path.
What's the best way to deal with this, please?
Get the master Primavera plan to tie these tasks t oend dates, set way in the future, but not affecting the schedule or to ty to stop Primavera putting these on the critical path which (presumably) should stop Primavera risk anayser seing them there too?
Also, in the primavera plan there isa problem whereby the task roll-ups sum to a greater duration than they should. Could this be due to the amount of open ended tasks in this plan too?
Many thanks
W