Baseline Target Schedule

Mary Lou HortonMember for 15 years 11 months
Created
2
1
0

I am using P6 V6.2. When I create a baseline using Create from Current Schedule it is not saving the latest / current schedule. Every month I need to generate snapshot target or new baseline of this month status. We use this to measure variance between each progress update. Is there a trick? (I was able to do this all the time with V7). Is there a toggle that I need to turn on/off?

2 replies

Oldest first
  1. 0
    Daniel Limson ·

    Hi Mary,To create a baseline,

    Hi Mary,

    To create a baseline, go to projects then follow this sequence, Maintain basleine, Assign baseline and then go to your Bars icon and tick either your primary or secondary baseline bar depending on what you need to see.

    Regards,

    Daniel

  2. 0
    Ron Beechey ·

    Mary Under Admin Preferences

    Mary

    Under Admin Preferences tab Earned value under Earned Value Calculations make sure you have "Budgeted values with current dates" selected.

     

    Hope this also helps