Updating Problems
In the Open Standard
Muhammad Usman AkramMember for 14 years 10 months
- Created
- 1
- 1
0
Dear all,
I am finding a problem that i had set a baseline for a project work programme. now when i am updating it with new data date the baseline milestones are also shifting. i want the baseline milestones to be shown as separate not shifted. can anyone help me out please ?