Multiple Critical Path
In the Open Standard
Henry ChiuMember for 15 years 3 months
- Created
- 7
- 2
0
Dear Planners,
Client keeps on sending letter to our company regarding our schedule. Client illustrated multiple critical paths from our schedule. Is there any filter and or option in P6 to produce multiple critical paths. I have tried the Floath Path Order - but this is not in line with the activities identified in the clients letter. Any other option or any enhancements required.
Thanks
Henry