Multiple Critical Path

Henry ChiuMember for 15 years 3 months
Created
7
2
0

Dear Planners,

Client keeps on sending letter to our company regarding our schedule. Client illustrated multiple critical paths from our schedule. Is there any filter and or option in P6 to produce multiple critical paths. I have tried the Floath Path Order - but this is not in line with the activities identified in the clients letter. Any other option or any enhancements required.

Thanks

 

Henry

 

7 replies

Oldest first
  1. 0
    Ryan Lytollis ·

    Henry, I am only aware of the

    Henry,

     

    I am only aware of the multi-float paths which is set up in the advanced scheduling tap, are your clients selecting activities and saying they are critical to the project?

  2. 0
    Ryan Lytollis ·

    Henry, I am only aware of the

    Henry,

     

    I am only aware of the multi-float paths which is set up in the advanced scheduling tap, are your clients selecting activities and saying they are critical to the project?

  3. 0
    Ryan Lytollis ·

    Henry, I am only aware of the

    Henry,

     

    I am only aware of the multi-float paths which is set up in the advanced scheduling tap, are your clients selecting activities and saying they are critical to the project?

  4. 0
    Ryan Lytollis ·

    Henry, I am only aware of the

    Henry,

     

    I am only aware of the multi-float paths which is set up in the advanced scheduling tap, are your clients selecting activities and saying they are critical to the project?

  5. 0
    Henry Chiu ·

    Ryan,Client identified as

    Ryan,

    Client identified as "First Critical Path" Second Critical Path, Third Critical Path and Fourth Critical Path. In identifiying these activities there must be a built in filter option in the P6 program that will enable to produce the grouping of these activities. Client Scheduler is well versed in P6, and is always attacking on this particular issue. I just recently use P6.

     

    Thanks

    Henry

  6. 0
    Khuong Do ·

    Hi,I wrote an article

    Hi,
    I wrote an article regarding How to display Multiple Critical path in Primavera P6.
  7. 0
    Zoltan Palffy ·

    group by total float then

    group by total float then filter for the groupings with the 3 lowest values 