How to see all Calnedars used in schedule

David BallMember for 14 years 8 months
Created
2
2
0

Hi,

 

I am using P6 and would like to find a way that I can see all Calendars used in a schedule without having to scroll through every activity.

Is there a quick and easy way to see what Calendars are used in the schedule?

 

Thanks very much

DFB

2 replies

Oldest first
  1. 0
    Mike Testro ·

    Hi David Surely there is a

    Hi David

    Surely there is a column that will show the calendar attached to the task.

    There is in every other software that I know.

    Best regards

    Mike Testro

  2. 0
    Gary Whitehead ·

    David,   The easiest way is

    David,

     

    The easiest way is to go to View > Group and Sort > Group by Calendar, then colapse the groups. (right click on the spreadhseet, and select "Collapse All")

     

    Might be worth inserting the "Activity Count" column, so you can see how popular each calendar is

     

    Cheers,

     

    G