Importing Units % Complete and Actual Dates
- Created
- 3
- 2
Hello all,
Any help would be very much appreciated.
I have a resource loaded P6 Plan that I would like to import actual start and actual finish dates into together with a percent complete (units %). I have run an export from the same P6 plan and I have tried to add a start date and a % complete to one of the activities as a test – for some reason when I import the same file (so I know all the fields are named correctly etc) P6 tells me that the import was successful, however none of the changes to the activity have taken place. Strangely the only change that takes place is an Actual Start is assigned, however this in not the date that I have allocated in the import,,,
Any ideas – I’m scratching my head here!
Many thanks
Jon
3 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?