Histogram & Report Not Correct
- Created
- 0
- 2
Hi Guys,
I am currently looking after a programme for an ongoing term contract on an oil refinery. We look after the elecrical side of things on the plant. We are currently mid way through a shutdown. I have been asked to produce a histogram so we can look at manning levels going forward.
The problem is that when I set the resource usage profile it is including hours that have been claimed at 100% previously. I update the programme on a daily basis and today is no different. I updated the progress from over the weekend into the programme up to 8am this morning.
I then scheduled the programme up to 8am this morning. The problem is that the resource usage profile (Measuring remaining early units) is extremely unaccurate (4173 Hours). When I filter out the items that are 100% complete it provides a more accurate amount of hours remaining to complete (553 Hours).
Is there any reason the histogram is showing such silly figures for my look ahead? We are very pushed for time here so a quick response would be very appreciated!!
Kind Regards,
David
Replies
Oldest firstNo replies yet. Be the first to answer.