Revised baseline having two different schedule percent complete for the same data date
- Created
- 0
- 3
Hi Everybody,
The MBSL was prepared and approved before 2 years & it worked fine. Recently my Master Baseline schedule (MBSL) was asked to revise due to Extension of Time. I revised my MBSL by inserting new milestones & corresponding links also been changed.
Now my Problem is, when I start to update i get 2 different schedule percent complete for the same data date.
ie., on extracting the monthly cashflow in revised baseline I computed the monthly planned value. when I attach it to the updated schedule with actuals by making a copy of revised baseline report I get different value, not as same as planned value obtained through cash flow. But i hope it should match
There was no change in resource assignment only links have been changed.
Please help me to fix this issue
Best Regards,
Akbar
Replies
Oldest firstNo replies yet. Be the first to answer.
Log in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?