Delete all relationships

Aymen BEN YOUSSEFMember for 18 years 2 months
Created
6
5
0

Hello Planners,

Is there an easy way to delete all relationships from a schedule in P6.7. I used to do it with global change in P3 but it doesn't works in P6.7 !!!

P6.7 global change is not efficient !!

Regards,

Aymen

6 replies

Oldest first
  1. 0
    Sm Pum ·

    Aymen BEN YOUSSEF  Salam To u

    Aymen BEN YOUSSEF 

    Salam To u Aymen.

    Not a big issue.Copy ur project in project window and then paste their.Just check of the option of Resources during coupying.

     

    Regards

  2. 0
    Aymen BEN YOUSSEF ·

    Hi SM PUM,Thank you for your

    Hi SM PUM,

    Thank you for your reply.

    I am looking for a way to do it without creating a new project. 

    Regards,

    Aymen

  3. 0
    Mike Testro ·

    Hi Aymen Why would you want

    Hi Aymen

    Why would you want to delete all the links?

    It seems a daft thing to do.

    Best regards

    Mike Testro

  4. 0
    Aymen BEN YOUSSEF ·

    Hi Mike,I am using Excel to

    Hi Mike,

    I am using Excel to edit quickly the relationships, I used to do it in P3 without facing any problem but I have to delete all the relationships before importing excel data (by doing a global change in P3).

    Many thanks,
    Aymen

  5. 0
    Rafael Davila ·

    duplicate ... see above

    duplicate ... see above

  6. 0
    Rafael Davila ·

    Because P6 does not gives the

    Because P6 does not gives the user direct access to any relationships table as other software do you can explore the use of Logicleague By Ron Winter as a way to overcome this limitation.

    http://scheduleanalyzer.com/ll_brochure.htm

    Will not be as easy and powerful as if implemented within the software itself but you will be able to do more things others are used to, like being able to switch on and off relationships and very common things like filter for float and deleting all relationships at a single click of the mouse.