Organogram in P6

Planning guyMember for 15 years 3 months
Created
1
2
0

Hi ,

I have one question...

In P6 , lets suppose i have multiple projects , Every project has its own organizational hierarchy (OBS)..... and for example i select one project and only want to take out the print of this projects hierarchy (not all) ... how can i ??... its shows all projects hierachy........How i do that . i only want to see this selected project organizational hierarchy.....?

 

I hope i have cleared my question.......

Regards

Planning guy

1 reply

Oldest first
  1. 0
    Arend Woltjer ·

    Hi planning guy,   may be the

    Hi planning guy,

     

    may be the top button in the OBS screen that says; Display: All OBS elements. does the trick for you?

     

    Regards,

    Arend