Baseline Issue
- Created
- 5
- 2
I have a project that is progressed for 1 year and we are rebaselining the project. We have taken an update project from the previous week and adjusted tasks to level the resources. We used the remaining budget hours by resource to level the work. I then Open the current updated project, maintain baseline and insert the updated project. I then assign a baseline and expect to see the same resource loading as was adjusted when I review the resource bar usage. But I am not getting the same leveling. I have set my admin to use current dates and the project is set to reset Original duration to remaining. BUt not getting what I would expect. Anyone have any ideas