Help w/ resources
- Created
- 1
- 1
Once I have my resources set up. How do I track them between projects. If I have so many units budgeted for each project how can I tell if I have to many guys on one project (overallocated?) and move to another project that needs help. Also how do I link projects together so for instance I can't have 1 laborer (JOHN SMITH) at 2 jobsites at the same time.
In summary, I have a "pool" of people set up as resoureces, I want the job to be as efficient as possible and I would like primavera to tell me what jobs laborers need to be moved to.
I bought the book by Paul.E Harris so if you could direct me to what chapter this is in that would be great.
Thanks everyone!
1 reply