Print Primavera P6 calendars

Brian SmithMember for 14 years 2 months
Created
3
1
0

 

Hi everyone,
 
Is there any way to print calendars in Primavera P6? What I would like to achieve is to be able to print a page that contains P6 monthly calendars from the project start date to the project end date. I have not found any option to do this in P6.
 
Thanks

3 replies

Oldest first
  1. 0
    Rafael Davila ·

    Printing the whole month is

    Printing the whole month is unnecessary and inefficient, you shall look for printing calendar exceptions as this in combination with the calendar weeks shall be enough. When exceptions are on consecutive days you shall print only the exception range but not every day for that exception.

    Just imagine hundreds of named resources, each with its own vacations, insane to print the whole calendar for each one. Just imagine if you have some resources with several half days off for training unrelated to any specific job. 

    Look on your software custom reporting capabilities. 

    Be green, save some trees.

    If the above is not good with P6 and you cannot find a direct way try the following.

    http://comviz.com.au/products/comvizcalendar/

  2. 0
    Leo Man ·

    Change the project  to p3

    Change the project  to p3 format then print the calendar there , i searched alot ,this is the only way i found.

  3. 0
    Mimoune Djouallah ·

    here is a free macro that

    here is a free macro that print the calendars from an xer file.

     

    https://code.google.com/p/xer-reader/

     

    regards

    mimoune