P6 Version 8.2 vs Microsoft SQL database server 2005

Siva GaneshMember for 14 years 10 months
Created
8
6
0

Hi everyone,

I was working with P6 V6.1 with the Database Microsoft SQL server, now i have updated Primavera to Version 8.2. When i run the Primavera program the database is not supporting. The report comes as:

The application and database versions do not match.
Click Exit to close the application.
Primavera P6 Professional R8.2 8.2.0
Expected database version: PMDB,0820.0001.0001
Current database version: PMDB,0600.0011.0001

Please help me to sort out. I have more schedules in my old database. I need to recover it.

8 replies

Oldest first
  1. 0
    Siva Ganesh ·

    Hi chris,I have followed your

    Hi chris,

    I have followed your steps but still have a small problem.

    Once i run the bat file, i have been asked few things

    Administrative USer name -

    Administrative Password -

    Database name -

    I am not familiar with database problems. Kindly help me sir.

     

  2. 0
    Siva Ganesh ·

    Dear Chris,The report i got

    Dear Chris,

    The report i got was

    SQLServer Exception: The TCP/IP connection to the host failed.

    Connection refused to the host. Verify connection properties, check that an instance of SQL server is running on the host and accepting TCP/IP connections at the port

    Kindly advice.

    Siva

  3. 0
    Siva Ganesh ·

    HI chris,I have installed SQL

    HI chris,

    I have installed SQL server 2012 and i uninstalled database engine.

    Presently nothing is working out. Whether all my schedules would have deleted?

    am scared. my boss will fire me. help me out chris.

    Siva

  4. 0
    Khaled Elshaer ·

    This Page shows in details

    This Page shows in details how to install Primavera P6 on SQL server 2012. Step by Step with Screen shots. http://www.behance.net/gallery/Installing-Primavera-P6-R82-on-SQL-Server-2012/7136957
     

  5. 0
    Khaled Elshaer ·

    This Page shows in details

    This Page shows in details how to install Primavera P6 on SQL server 2012. Step by Step with Screen shots

    http://www.behance.net/gallery/Installing-Primavera-P6-R82-on-SQL-Server-2012/7136957

  6. 0
    Khaled Elshaer ·

    This Page shows in details

    This Page shows in details how to install Primavera P6 on SQL server 2012. Step by Step with Screen shots

    http://www.behance.net/gallery/Installing-Primavera-P6-R82-on-SQL-Server-2012/7136957

  7. 0
    Michael Bengano ·

    hi.gud day..i just want to

    hi.gud day..i just want to ask for your help.i want to install the latest version of primavera 8.2. the problem is when i start to install it, it says that i have to delete the older version of primavera to continue installing.but after i deleted the older version, the installation still stops and tells me again to delete the older version?thank you so much.

  8. 0
    Dieter Wambach ·

    Hi Michael There was a bug in

    Hi Michael

    There was a bug in MS-SQL server which didn't clean the registry properperly - I hope you used the uninstall feature.

    If there is no other software using MS-SQL server check your registry for entries from SQL-server and delete them.

    If there was Oracle database I never heard of this issue.

    Regards

    Dieter

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?