Printing Schedule to a PDF to be printed on Large Format Plotter??

Ryan RowlandMember for 15 years 8 months
Created
1
1
0

Is it possible to create a custom print size for a schedule so that it can be printed on one sheet, for instance w/ a 36" Roll Fed Plotter. The schedule to be printed is around 1000-2000 activities, so it would probably need to be 96" or greater in height. Is there a way to do this? Thanks,

1 reply

Oldest first
  1. 0
    Daniel Limson ·

    Hi Ryan,Certainly, you can do

    Hi Ryan,

    Certainly, you can do so, however with 1000 to 2000 activities, maybe you need several pages. The only thing you need to do is set the default printer to your plotter and reconfigure scale to fit your desired output.

    Regards,

    Daniel