Question about leveling resources and durations

Scott ParkerMember for 14 years 2 months
Created
1
2
0

I was wondering how to set my activities so that when I schedule and level my resources my durations change automatically?  I have been given the folowing information

 

Budgeted Hours for the activites

Available Manpower

Start date

Finish date

Set Calendar

 

I want to be able to play with my manpower and calendar to effect durations.  Hope this makes sence to someone.

 

Scott

1 reply

Oldest first
  1. 0
    Sm Pum ·

    In resource levelling Option

    In resource levelling Option "CHeck Off" Preserve schedule Early & Late Dates.

    regards