Question about leveling resources and durations
In the Open Standard
Scott ParkerMember for 14 years 2 months
- Created
- 1
- 2
0
I was wondering how to set my activities so that when I schedule and level my resources my durations change automatically? I have been given the folowing information
Budgeted Hours for the activites
Available Manpower
Start date
Finish date
Set Calendar
I want to be able to play with my manpower and calendar to effect durations. Hope this makes sence to someone.
Scott
1 reply
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?