Successor lag calendar
In the Open Standard
Alexandre Faulx-BrioleMember for 23 years 8 months
- Created
- 1
- 1
0
Hello Planners,
does somebody of you ever use the Relationship lag calendar option in the Schedule dialog?
it seems to behave the contrary the help files and Reference Manual describe.
As my client wants to schedule milestones 1 calendar month after the other, I tried to use this option to link milestone 1 and miletsone 2 with a FS link and a 1 month lag using the 24hour calendar; the result was not satisfying at all, horfull I would say
Any help will be highly welcomed
Alexandre