WBS Summary Question
- Created
- 4
- 1
I was wondering if it is possible to do the following. I have an activity that I would like to breakdown into three seperate sub activities. I have the estimated hours lets say 1500 hours for a total duration of 15 days. I would then breakdown the hours into each sub activity. I would then progress each Sub activity 500-500-500. I would then progress each sub activity. See below
Activity A1850 Summary 1500hr 15 days 65%
Activity A1850.1 First Activity 500 hrs 5 days 20%
Activity A1850.2 Second Activity 500 hrs 5 days 25%
Activity A1850.3 Third Activity 500 hrs 5 days 20%
From our accounting software I get the actual hours and dollars. I would like to be able to add these actuals into the summary as these hours are not broken down by sub activity. Also is there a way to add the budgets hours and duration in the summary and have them automatically calculate down into each sub activity. Is there a way to do this?
Thanks in advance.
4 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?