Gary,
1) Print as pdf -this will maintain the dates, but you will struggle to show all other info in a legible view (costs, activty codes, early & late dates, float, constraints, etc):I need to submit the Primavera file, a pdf is not allowed.
2) Ensure "schedule automatically when a change affects the dates" option from schedule options is not checked, then delete the relationships. All the dates will be maintained until/unless you hit F9:This is being undone when I am saving the file.
3) Give all activities a SNET constraint = early start date, then delete the relationships.: A SNET is something I cannot find amonst the possibilities in the constraints
4) Make all actvities complete, then delete the relationships:This will take way too long...
Do you have another idea?
Thanks for the replies guys!