Can't get P6 to assign Baseline dates

John KellyMember for 15 years 3 months
Created
4
3
0

Hi folks,

I searched the forums for an answer to this and couldn't find anything hence the new post.

I have multiple programmes, A baseline and monthly updates. 

I have assigned the monthly update of March as a baseline to the April update, (reason being i want to show alippage against previous month rather than against baseline)

I have added the baseline as usual using the 'maintain' function then assigned as Primary baseline, problem is though that the planned dates (BL1) aren't showing as the dates that i can see when i look at the March programme, i think its taking the dates from the original Baseline somehow.

 

Anybody any ideas?

 

Thanks in advance

4 replies

Oldest first
  1. 0
    Raymund de Laza ·

    John,Open March Program and

    John,

    Open March Program and perform Global change by equating Planned Dates = Start and Finish dates then assign as baseline to April. This will give you what you requires.

    Hope this will help.

  2. 0
    Gary Whitehead ·

    John, A common issue, which

    John,

    A common issue, which Paul Harris has addressed very well is this presentation:

    http://eastwoodharris.com/DL/TP/110616_P6_V7_What_Baseline_Bars_am_I_Displaying.pdf

     

    Cheers,

     

    G

  3. 0
    Zahid Shaikh ·

    After maintain baseline did

    After maintain baseline did you do assign baseline?

  4. 0
    Zoltan Palffy ·

    what columns are you

    what columns are you displaying ?

Log in or join to reply