Baselined dates change when assigned back to the plan

Nathan CarterMember for 14 years 4 months
Created
1
2
0

I have amended some activities on the restored baseline and the dates are all accurate.  When I then assign the baseline back to the main plan a couple of the baseline dates change back/ close to the data date.  This only happens to a couple of activities. Any ideas?

Also I have tried adding new activities to the restored Baseline plan but when it is assigned to the main plan the activity is not present?  I have checked all filter etc but cannot see a reason why.

Any help on either of these would be great.

 

Regards

Nath

1 reply

Oldest first
  1. 0
    Ronald Winter ·

    Perhaps you are not actually

    Perhaps you are not actually looking at the baseline schedule that you think you are.  Try http://www.planningplanet.com/forums/primavera-version-pm5-pm6/528595/cant-get-p6-assign-baseline-dates for more on this.  Good luck!

Log in or join to reply