Filters. For the MASTERS only.
- Created
- 13
- 4
Hi folks
I am having some issues when creating a very selective filter. The information I want to display is very specific but to add salt to injury I can only use one filter and not a combination of them. As you know Reports in P6 only allow to create and apply one filter only.
The criteria is very straigh forward. What I want to display is the activities that should have finished before the data date.
Here is the sieve:
- 'Activity Type' = Task dependant (I don't want milestones).
- 'BL Project Finish' less than or equal to Date Date.
- 'Activity Satus' not equal to completed (I want to show both not started and not completed).
There is no need here to sub group filters. All lines will be under 'All of the following'.
After setting this filter and applying only this filter the program wrongfully shows nothing. There are certainly activities to be shown.
Any help will be appreciated.
Cheers,
Frances.
13 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?