Is baselining the only way to create multiple versions?
In the Open Standard
Rizwan SiddiqiMember for 13 years 11 months
- Created
- 2
- 3
0
Hello Planners,
Question for you guys. I am used to MS Project where I could Save As to multiple versions of the plan as I was playing with the dates in the plan.
1) With PV, I know I can baseline to take a snapshot of the plan. Is there another way to take a snapshot and restore incase my "Schedule" ends up changing dates I didnt intend to change?
2) Need to research this but, is there a clean way of restoring Baseline plan (including additional task, resources etc) as the current plan?
Thanks,
Riz