Is baselining the only way to create multiple versions?

Rizwan SiddiqiMember for 13 years 11 months
Created
2
3
0

Hello Planners,

Question for you guys. I am used to MS Project where I could Save As to multiple versions of the plan as I was playing with the dates in the plan.

1) With PV, I know I can baseline to take a snapshot of the plan. Is there another way to take a snapshot and restore incase my "Schedule" ends up changing dates I didnt intend to change? 

2) Need to research this but, is there a clean way of restoring Baseline plan (including additional task, resources etc) as the current plan?

Thanks,

Riz

2 replies

Oldest first
  1. 0
    Rizwan Siddiqi ·

    Note, I should say "The Best

    Note, I should say "The Best Way to version", not "Only". I am hoping to learn the best way and not just other options that one would not really use.

    Thanks.

    Riz

  2. 0
    Håkon Haukebøe ·

    Dont know if its the best

    Dont know if its the best way, but I copy/paste the project in the EPS.

     

    Haakon

Log in or join to reply