PM5 SP5

Glen StauntonMember for 21 years 2 months
Created
1
2
0

morning

 

Anyone know of a way to complete the physical percent complete from 0 to 100 on a finish (or start) milestone? I have feeling you cant, but perhaps I'm wrong. The percent complete type is physical.

 

Thanks

 

Glen

1 reply

Oldest first
  1. 0
    Johannes Vandenberg ·

    Hi GlenJust update the

    Hi Glen

    Just update the activity as you would normally do. Tick the box started in the status tab. Finish shall be automatically updated.

    Regards

    Johannes