Same calendar for activities AND resources?
In the Open Standard
Jenny IngcoMember for 14 years 9 months
- Created
- 3
- 1
0
Dear Planners,
How I can assign same calendar for my activities AND resources? Because when I go to resourse calender there is no option to use project calender there are only Global and resourse calenders. So, do I need to greate new calender in the Global and make it exactly same the one in project calender? I am using P6 v.7..
Thank you for any advise,
Hanson
3 replies
Oldest firstLog in or join to reply