Skip to content

Same calendar for activities AND resources?

Jenny IngcoMember for 14 years 9 months
Created
3
1
0

Dear Planners,

How I can assign same calendar for my activities AND resources? Because when I go to resourse calender there is no option to use project calender there are only Global and resourse calenders. So, do I need to greate new calender in the Global and make it exactly same the one in project calender? I am using P6 v.7..

Thank you for any advise,

 

Hanson
 

3 replies

Oldest first
  1. 0
    Shah. HB ·

    Hi HansonOpen the project you

    Hi Hanson

    Open the project you created and choose enterprise menu, select calendar option, where you can create calendar pertained to project specific.

    Assign calendar to one activity first and then use fill down option to assign all the required activities

    Cheers

    Shahul

  2. 0
    Jenny Ingco ·

    Dear Shahlul, Thank you very

    Dear Shahlul,

    Thank you very much for your help. I just was wondering how I can use same calendar for project activities and recourses.. Example if the construction calendar under project with 5 working days per week and 8hrs/day and recourses assigned to this activities can work 7 days per week that will cause problems in the schedule. So I believe we should create new calendar in recourses with same working days and hours in project calendar.

     Thank you,

     HANSON

  3. 0
    Jenny Ingco ·

    Thank you.

    Thank you.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?