Primavera P6 schedule % complete not calculated

Antonio OrsiniMember for 13 years 9 months
Created
3
1
0

Dear all,

im new in primavera P6 .

When i update the progress of the project,  the p6  calculates the progress of the activities but does'nt calculate  the total  % progress complete or WBS  % progress complete .  can someone help me?

thank

3 replies

Oldest first
  1. 0
    Alexandre Faulx-Briole ·

    Hi Antonio,open the View,

    Hi Antonio,

    open the View, Group and Sort dialog box

    check the Show Group Totals option

    also make sure you are using the Duration % complete field and not the Activity % complete

    Alexandre

  2. 0
    Antonio Orsini ·

    Thank Alexandre.i didnt use

    Thank Alexandre.

    i didnt use Duration % complete field. now is ok. But why rhe Schedule % complete is 0??

    thank

     

  3. 0
    Omid Khan ·

    for activities. schedule %

    for activities. schedule % complete is calculated using the following formula:

    Schedule % Complete(Act) = ( [Data Date] – [Baseline Start] ) / ( [Baseline Finish] – [Baseline Start] )
    
    as you see the above formula is not related to the cost of the activity but
    for wbs elements schedule % complete is calculated using the following formula

    schedule % complete = pv/bac

    as you see the above formula is related to the cost of the wbs element

    so if the cost of a wbs element is 0 u get 0 for schedule % complete

    if u want to have a good grasp of the issue read the following link:

    http://www.plannertuts.com/primavera-p6-tutorials/primavera-p6-schedule-percent-complete-guide-1-1180/