Constraints in P6
In the Open Standard
V KuttyMember for 15 years 9 months
- Created
- 8
- 4
0
The Planner on one of my projects has been supplying with programs with constraints in. I wouldnt have minded upto 10 soft constraints per 1000 incomplete activities but the number is about 23-30 % of incomplete. I am curious to know
- If there is a acceptable number of constraints?
- What is the risk of using constraints in a Program? Is there any material out there on this which I can use to inform my knowledge?
Thanks,
8 replies
Oldest firstLog in or join to reply