Showing "day of the week" in separate column next to date

Bob FodenMember for 19 years
Created
2
2
0

Hi,

Does anyone know if it is possible to show the day of the week associated with a date in P6V7 preferably in a separate column to the date ?

Thanks

Bob

2 replies

Oldest first
  1. 0
    Kumar S ·

    Hi Bob, Here is the answer to

    Hi Bob,

    Here is the answer to your query.

     

    http://www.rpc.uk.com/perch/resources/rpctip16.pdf

     

    Regards,

     

    Kumar

  2. 0
    Alexandre Faulx-Briole ·

    Hi Kumar,"Day of Week" trick

    Hi Kumar,

    "Day of Week" trick works perfectly; I made it work with P6 "English Speaking", then I had to customize the Global Change to have it work with P6 "French Speaking", as the "Start" parameter does not translate automatically; now, I have 2 Global Changes, 1 for English, 1 for French

    Thank you!

    Alexandre