Skip to content

Earned Value Cost not appering on update once baseline assigned!

Jojie PepitoMember for 17 years
Created
0
3
0

Urgently need help;

I did a latest update for bi-weekly reporting , after my updation i assigned the baseline & found out that the earned value cost for two activities which are 100% complete does not replect in earned value column only the actual cost is appearing, so after the baseline assigning the budget at completion is different from at completion total cost, ...what happened, i need your help?

Replies

Oldest first

No replies yet. Be the first to answer.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?