dates keep on changing whenever i press F9

Russell ManubaMember for 13 years 5 months
Created
8
2
0

ALL,

Can anyone help me how to keep the activity dates fixed. Everytime i press the F9 some dates are automatically adjusting on their own. I have to replot each activities again and again. 

I'm all done with the putting dates and relationships then when i press F9 all dates become distorted. 

Thanks you for your help and i would appreciate your response

 

Russell

8 replies

Oldest first
  1. 0
    Ryan Stuttard ·

    This is almost certainly a

    This is almost certainly a problem with constraints as well as relationships between activities. Make sure to check the status tab under activity details and check which constraints you have in place, or maybe need to put in place.

     

    Good luck


    Ryan

  2. 0
    Ryan Stuttard ·

    Edit*

    Edit*

  3. 0
    Neil Hendry ·

    Hi Russel,  when you press F9

    Hi Russel,  when you press F9 you are scheduling your programme therefore any activities that are not held in place by either constraints or logic will move to the earliest date that it could be done - i.e the data date.

    Try to make sure alll your activities have predecessors and successors in the first instance rather than put constraints on everything.

    hope this helps

    Neil 

  4. 0
    Russell Manuba ·

    Thanks Neil and Ryan!  I

    Thanks Neil and Ryan! 

     

    I already revised the schedule and ensure all activities are connected (thanks for the advice). Though there 2 or 3 activities which i don't know where to connect so i put a  "finish on" constraint to remove total float. 

     

    However, i have this other problem. After putting all activities into place (dates, duration and relationship), then i put actual dates and press F9 set my data on 30th of April. Our project is supposed to finish on June 30 2014 but when i press F9 end date automatically moved to October.

    How can i fix end date to June 30 2014? 

    Thanks so much again for your brilliant advice. 

     

    Russell

  5. 0
    Neil Hendry ·

    Hi Russell, Your planned

    Hi Russell, Your planned finish date is later than your contract finish date because your critical path is longer than the amount of time you have. I would suggest reviewing your critical activities to see if you can shorten or overlap any of them enough to meet your desired completion date.
  6. 0
    Russell Manuba ·

    Thanks Ryan. very helpful

    Thanks Ryan. very helpful info. 

  7. 0
    Mike Testro ·

    Hi Russell Also check that

    Hi Russell

    Also check that you do not have a logic loop.

    Best regards

    Mike Testro

  8. 0
    Henrik Schneider ·

    I have a simular problem. I

    I have a simular problem.

    I have a constrain - "Mandatory Start", if the activity has been startet and I press F9 the start date shiftes back to datedate.

    If the activity is NOT startet, the date (mandatory start) will be kept as I typed it.

     

    Any idea how I can ensure a mandatory start date that will not move after pressing F9?

     

    In advance - thanks

     

Log in or join to reply