FS

Alain De leonMember for 14 years 4 months
Created
4
2
0

How to default (FS) to start new activiy 1 day after finish date. ex. june 18 is finish date and the new actvity must start june 19. Thanks, 

4 replies

Oldest first
  1. 0
    Santosh Kumar Prasad ·

    Link Activities

    Link Activities

  2. 0
    Gary Whitehead ·

    If you have a chain of these

    If you have a chain of these activities which must each be linked by FS with zero lag, you can highlight them all, right click, and choose "link activities"

     

    It will link them in the order they appear on the screen

  3. 0
    Alain De leon ·

    thanks a lot SANTOSH KUMAR

    thanks a lot SANTOSH KUMAR PRASAD and Gary Whitehead, God bless

  4. 0
    John Sims ·

    you can also link them by the

    you can also link them by the order you select them.