Absence of proper Longest Path in a Schedule with many milestones

Gulshan KriplaniMember for 17 years 6 months
Created
2
3
0

We are making a schedule for a building with many contractual milestones which are given constraint "finish on" in P6. These milestones are linked with each other with FS relationship and lag 0. However, with this arrangement the schedule is not showing a proper longest path. Is there any remedy for the same.

2 replies

Oldest first
  1. 0
    Santosh Kumar Prasad ·

    Hello Gulshan Firstly check

    Hello Gulshan Firstly check schedule Open ends, if there work on it with proper logic. After that link your milestone A) start Milestone : link with group latest start successor activity with SS 0 lag relationship. B) Finish Milestone : link with group last finish successor activity with FF 0 lag relationship.
  2. 0
    Ronald Winter ·

    Gulshan, I presented a paper

    Gulshan,

    I presented a paper on this topic at the 2005 AACE conference titled, “Managing Multiple Milestones.”  You can find a copy of it at http://www.ronwinterconsulting.com/published.htm.  Good luck!