Predecessor and Successor

Yifei 87Member for 13 years 7 months
Created
4
4
0

Dear Sirs,

For P6, say Task A is the predecessor as Task B and Task C is the successor for Task B.

If I delete Task B, can the linking from Task A-Task B become Task A to Task C?

Thank you

4 replies

Oldest first
  1. 0
    Mike Testro ·

    Hi YifeiYesBest regardsMike

    Hi Yifei

    Yes

    Best regards

    Mike T.

  2. 0
    Gary Whitehead ·

    Yifei, If you delete Task B,

    Yifei,

     

    If you delete Task B, you will have to manually add the link from Task A to Task C

    If you instead dissolve Task B, Primavera will automatically add the new link for you

  3. 0
    Mike Testro ·

    Hi GaryAlternatively you

    Hi Gary

    Alternatively you could change task B into a milestone to leave a record of the change.

    Best regards

    Mike Testro

  4. 0
    Yifei 87 ·

    Thank you very much.  I think

    Thank you very much.  I think this had solve my problems.

    Have a nice day.