Hi All,

I'm cleaning up a database and I was unsure if there was an easy way to change global calendars to project calendars?

All help/ thoughts appreciated.

Regards, Kylee.

2 replies

Oldest first
  1. 0
    Paul Harris ·

    KyleeYou may not change them

    Kylee

    You may not change them only copy them.

    Regards

    Paul E HarrisBSc Hons,
    Certified Cost Engineer, PRINCE2 Practitione
    Managing Director and President
    Eastwood Harris Pty Ltd, Australia
    www.eh.com.au,  www.eastwoodharris.com, www.primaskills.com.au  and www.primavera.com.au
    Project Control Consultants and Planning and scheduling software book and training material publishers

  2. 0
    Arnold Puy ·

    Hi Kylee,The only way you can

    Hi Kylee,

    The only way you can change your calendar from global to project is by using the SDK (Dictionary6.xls), otherwise, Mr. Paul suggestion is to copy the global to project calendar is the best way.

    Thanks

    Arnold

     