Level of Effort Activities

Kylee FosterMember for 19 years 2 months
Created
1
1
0

Hi All,

It seems if I assign roles to a level of effort activity before I schedule it so the activity is of the correct duration, the distribution of the role will remain on the initial duration of the activity even after I schedule.

Can anyone verify this for me?  Are there other tricks with this? 

Thanks and Regards, Kylee.

1 reply

Oldest first
  1. 0
    Raymund de Laza ·

    Kylee,Suggests to do the

    Kylee,

    Suggests to do the following:

    1. In User Preferences ... Resource Analysis .. Review the "Interval for Time distributed resource calculations" if its matching your Time Scale.

    2. After scheduling, Remove the Roles asssigned and re-assign.

     

    Regards,