Level of Effort Activities
In the Open Standard
Kylee FosterMember for 19 years 2 months
- Created
- 1
- 1
0
Hi All,
It seems if I assign roles to a level of effort activity before I schedule it so the activity is of the correct duration, the distribution of the role will remain on the initial duration of the activity even after I schedule.
Can anyone verify this for me? Are there other tricks with this?
Thanks and Regards, Kylee.
1 reply
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?