Application Event Error - How do you correct?

Kim ForbesMember for 15 years 6 months
Created
2
2
0
PRM DBAccess Error: Database Server Error: ORA-12952: The request exceeds the maximum allowed database size of 4 GB ORA-06512: at "ADMPRM$PM.RT_UDFVALUE_DEL", line 3 ORA-04088: error during execution of trigger 'ADMPRM$PM.RT_UDFVALUE_DEL'

2 replies

Oldest first
  1. 0
    Pranab Kumar Deb ·

    Hi Kim, You have reached the

    Hi Kim,

    You have reached the maximum allowable space in Oracle database. Solution is to move to SQL database.

    Thanks,

     

    Pranab

  2. 0
    Rafael Davila ·

    http://www.ronwinterconsultin