Skip to content

P6 ver 7 Calendars

Kylee FosterMember for 19 years 2 months
Created
2
2
0

Hi All,

I've a curiousity for you and I hope you can answer for me.  I'm cleaning up an old database and reducing the number of global calendars to what is practical/needed.  When a calendar cannot be deleted because it is assigned but the Utilization comes up empty for Projects and Resources, why is that?

All help appreciated.

Regards, Kylee.

2 replies

Oldest first
  1. 0
    Mohamed Kyasudeen Mohamed Hanifa ·

    the Utilization comes up

    the Utilization comes up empty for Projects and Resources, why is that?

     

    Can u explain clearly this part....

  2. 0
    Kylee Foster ·

    Hi All, The answer is

    Hi All,

    The answer is apparently that the calendars are assigned to baselines that are not found/ shown in the utilisation.  To find these I need to use scripts.

    Regards, Kylee.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?