P6 ver 7 Calendars

Kylee FosterMember for 19 years 3 months
Created
2
15
0

Hi All,

I've a curiousity for you and I hope you can answer for me.  I'm cleaning up an old database and reducing the number of global calendars to what is practical/needed.  When a calendar cannot be deleted because it is assigned but the Utilization comes up empty for Projects and Resources, why is that?

All help appreciated.

Regards, Kylee.

2 replies

Oldest first
  1. 0
    Mohamed Kyasudeen Mohamed Hanifa ·

    the Utilization comes up

    the Utilization comes up empty for Projects and Resources, why is that?

     

    Can u explain clearly this part....

  2. 0
    Kylee Foster ·

    Hi All, The answer is

    Hi All,

    The answer is apparently that the calendars are assigned to baselines that are not found/ shown in the utilisation.  To find these I need to use scripts.

    Regards, Kylee.