Revenue Forecasting
- Created
- 4
- 1
Hi all,
I'm creating a cash flow programme, and am struggling to find the most appropriate way to use the cost fields.
Effectively, the programme has many activities which have an agreed selling price (Revenue).
For expenses, I think it is best to use the 'expenses' module to assign budget/actual dollar values against relevant activities. This allows me to monitor budget vs actuals, and I can also produce reports etc. No problems there.
However, there doesn't seem to be a suitable field for loading 'Revenue' figures (what we would claim from the Client). This is a fixed price contract, so the total Revenue for each activity is fixed.
I can see how the 'expenses' module could be used to manage this information, but there would be some problems with this:
1. it is already loaded with budget expenses (not Revenue).
2. Since it's a fixed price contract, I don't see the benefit of being able to monitor Budgeted Revenue and Actual Revenue separately, since they will be the same.
I have created a UDF (with 'cost' units) called Revenue, and loaded my selling price into it for each activity.
I figured I would just to a time-distributed report on this UDF, to show me my monthly Revenue.
BUT, P6 won't do time-distributed reports for UDF values!!!
I find that mind boggling! Surely there is a huge benefit in being able to produce time-distributed reports for any quantum (not just units or costs)?? Am I missing something here?
I'd appreciate any advice on using P6 for Costs and Revenue in the same programme.
Thanks,
Hugh
Specifically, I'm interested in forecasting incoming funds (Revenue).
It's in relation to a fixed price contract, so at the end of the project, the total Revenue will be fixed.
S
4 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?