Skip to content

Restoring and Converting Baselines in Primavera P6 Professional R7.0

Emily FosterMember for 15 years 2 months
Created
0
3
0

Managing Baselines in Primavera P6 Professional is a slightly different process than you would encounter in file based tools such as Microsoft Project. When you save a baseline in Microsoft Project, you are saving copies of dates, durations, resource assignments and costs to special fields within the project file. However, when you create a baseline in Primavera P6 Professional, you are actually creating a complete copy of the project, and then linking back to that project in order to display baseline values.

This article takes you through the differences and the process http://ow.ly/qYlTx

Replies

Oldest first

No replies yet. Be the first to answer.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?