Expected Remaining unit / time to be Zero
In the Open Standard
Vinod RaturiMember for 20 years 2 months
- Created
- 0
- 4
0
Hi ,
I recently updated an actvity as completed , and accordingly have remaining duration and remaining units as zero.
Howvever in resource tab , for the same activity i have remaining uint/ hr as 1 eventhough remining units are zero.
I was expecting even remining unit/ time as zero since there is no more to spend on that actvitiy.
Hope some one can throw some light on this.
Thanks in advance,
Vinod Raturi
Replies
Oldest firstNo replies yet. Be the first to answer.
Log in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?