View of All Costs by Cost Account
- Created
- 1
- 3
Hello Planners,
Is there a view in P6, that allows me to view ALL costs, grouped as per the 'cost account' hierarchy?
E.g. I have some activities cost loaded with resources, and other activities cost loaded with expenses.
Some activities are loaded with both.
All costs (resource and expense) are assigned to an element in my 'cost account' structure.
Using the 'Project Expenses' view, I can get a nice grouping of expense costs (not resource costs) by cost account.
Using the 'Resource Assignments' view, I can get a nice grouping of resource costs (not expense costs) by cost account.
Is there a way of getting a view of ALL costs, grouped by cost account?
Thanks,
Hugh.