Skip to content

Primavera - Resources over budget / histograms

Lee JohnsonMember for 12 years 9 months
Created
1
2
0

Hi;

I have resources set up within my project.

 

Project Manager, Engineer etc.

 

Project manager has an 8hr day, Engineer has a 4hr day.

In my stacked histogram it shows that both are overloaded as follows.........

 

Project Manager requires 16hrs per day

Engineer requires 24hrs per day.

 

Its obvious to see that i will require 2 project managers, and 6 engineers per day, but is there a way of having the P6 histogram tell me how many people i would require, rather than tell me how many hours i am over budget?

1 reply

Oldest first
  1. 0
    Tyler Babin ·

    Lee, With thre resource usage

    Lee,

     

    With thre resource usage profile open right click in the graph area,

    Select: Resource Profile Usage Options

    once the dialog box opens select the graph tab

    once on the graph tab, under additional display option, click the box near the botton labeled calculate average.

    under divide intervals by click the box labeled: base on hours per time period.

    This should show you how many people per time period it will require.

     

    Hope this Helps,

    Tyler 

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?