Primavera - Resources over budget / histograms
In the Open Standard
Lee JohnsonMember for 12 years 9 months
- Created
- 1
- 2
0
Hi;
I have resources set up within my project.
Project Manager, Engineer etc.
Project manager has an 8hr day, Engineer has a 4hr day.
In my stacked histogram it shows that both are overloaded as follows.........
Project Manager requires 16hrs per day
Engineer requires 24hrs per day.
Its obvious to see that i will require 2 project managers, and 6 engineers per day, but is there a way of having the P6 histogram tell me how many people i would require, rather than tell me how many hours i am over budget?